 |
| Construction |
|
| Reclamation |
| The landfalls of West Kowloon Peninsula and Sai Ying Pun
were constructed on areas of reclamation. At Sai Ying Pun the reclamation
was placed in 1988 and no long-term settlements are expected. The West Kowloon
reclamation was placed in 1993, using pumped marine sand. Future settlements
are not expected to be significant. Settlement points have been established
and ongoing monitoring continues. |
| |
| Sai Ying Pun Cut-and-cover Tunnel |
| Top-down construction within diaphragm wall was used
at Sai Ying Pun due to the limitations of space. The top roof slab
was constructed between the two walls and central steel piles were driven
to support it until the dividing wall could be constructed. The base slab
was then placed, supported by shear keys into the diaphragm walls.
|
| One of the major concerns was the control of water seepage through the
diaphragm walls and the roof and base slabs. Precast wall panels were erected
along the diaphragm walls leaving a 400 mm gap. Half round drainage channels
have been provided at the top of the profile road barrier between the wall
and the panel and these were drained at intervals into the road drainage
system. |
| |
| West Kowloon Cut-and-cover Tunnel |
| The cut-and-cover tunnel linked the immersed tube to the
open approaches and the toll plaza area. It was constructed on newly
reclaimed land by the conventional bottom-up method, using a temporary cofferdam
with diaphragm walls and steel cropping. The open approach structure
was constructed in an open-cut, using a cement bentonite cut-off wall. The
base slab structure was up to 2 m and was designed to resist the uplift
pressure and floatation generated by the ground water in the reclamation
site. |
| |
| Immersed Tube Tunnel |
| Construction of the immersed tube units took place using steel shutters
in a controlled way, and by employing good concrete curing and quality control. Crack
widths were specified to be less than 0.2 mm. As soon as the units
were confirmed in a final position, the alignment holes were projected with
hydraulic jack to draw the two units together to create an initial seal
to the rubber gasket. The water between the two units was then pumped
out and the unbalanced hydrostatic pressure forced the units together and
compressed the rubber gasket into a watertight joint. Once the unit was
in position and was supported on temporary vertical jacks at its pre-end,
sand was then pumped into the space below the unit to provide a permanent
foundation. The main trench was then backfilled. Protected rock
armour was then placed on top of the units to prevent damage. |
| |
| Reference : |
Thomas Telford Limited - Journals on Line. "Civil Engineering Special
Issue : Hong Kong International Airport, Part 2: Transport Links /
November 1998 - Paper 11526 Western Harbour Crossing, Hong Kong -
a successful BOT model" |
|
| |
|
| ¤¤¤åª© | Top | Back to Introduction
| Home
| Terms of Use | Privacy
Policy |
| Copyright © 2007 Western Harbour Tunnel
Company Limited. All Rights Reserved. |